REQUIREMENTS FOR BUILDING PERMIT
- Clearance from the barangay where the proposed site is located (For Bldg. Permit)
- Locational Clearance
- Certified true copy of TCT
- Tax Declaration (2016)
- Tax Clearance (treasurer’s office)
In case applicant is not the registered owner
- Requirements b1 to b3
- Contract of lease, or
- Contract of sale, or
- Deed of Absolute Sale or
- Affidavit of consent of the registered owner or heirs (notarized)
- Location Plan (from the Office of the Assessor)
- ECC (If project is required under DENR regulation
- Affidavit of Setback (notarized)
- Road Right of Way Clearance (Structure is along the Road. Provincial/National)
- Regular documents
- a) Building Permit application Form (5 copies)
- b) Sanitary and Plumbing Permit Application form (5 copies)
- c) Electrical permit Application Form (5 copies)
- d) Mechanical Permit Application Form (5 copies)
- e) Bill of Materials and Specification (5 copies)
- f) Building Plan
- Architectural plan
- Fire and life safety master plan
- Electrical plan
- Plumbing plan
- Structural plan
- Community Tax Certificate (Cedula)
- 9. Paper Fastener
- Long Folder
- CONSTRUCTION SAFETY & HEALTH PROGRAM (DOLE)
- Fire Safety Evaluation Clearance (FSEC) – from the Bureau of Fire Protection
- Zoning Clearance (MPDC)